The Netherlands has opened bidding for two offshore wind farm sites, IJmuiden Ver Gamma-A and Gamma-B, with a combined capacity of 2 GW. The Netherlands Enterprise Agency (RVO) will accept bids until 10 December 2026. To keep developers interested as costs and risks have risen across the sector, the government has raised the maximum support prices to €117/MWh for Gamma-A and €116/MWh for Gamma-B. The European Commission approved up to €9.45 billion of state aid for the two projects in November.
Two-Week Bidding Window
The bidding window opened on 26 November 2026 and closes at 17:00 on 10 December. Each site can accommodate a wind farm of about 1 GW. The winning bidder for each site will receive a permit to build and operate the farm. Developers can either apply for a subsidy or bid to build without one.
Gamma-A lies about 53 km off the Dutch west coast and covers 129 square kilometers. Its subsidy budget is about €4.76 billion. Both sites are part of the IJmuiden Ver Wind Farm Zone, which has four sites and can hold around 6 GW of capacity. Permits for the Alpha and Beta sites were awarded in 2024, and the government decided in April 2026 to open Gamma-B alongside Gamma-A.
Higher Price Caps
Conditions in the offshore wind market have changed sharply in recent years, as higher costs and greater risks have weighed on project economics. In June 2026, the Dutch government responded by raising the maximum tender prices. The cap for Gamma-A rose from €104/MWh to €117/MWh, and the cap for Gamma-B from €103/MWh to €116/MWh. The increase marks a shift for a market that previously awarded sites without subsidy.
When it raised the budget, the Dutch Cabinet said market consultations showed enough developer interest to support both tenders. It said the two sites would make a significant contribution to the country's energy security. The Cabinet also restated its commitment to a predictable rollout of offshore wind. Bidding levels over the next two weeks will show whether the higher caps were enough.
EU State Aid Approval
In mid-November 2026, the European Commission approved a Dutch scheme worth up to €9.45 billion to support electricity from the two wind farms. Support takes the form of a variable premium paid on top of market revenues when power prices are too low to cover production costs. It can be paid for up to 15 years from the start of operations. If market prices rise above a project's agreed strike price, part of the support must be paid back.
Under the scheme, bids offering to build without support are considered first. Only if none come in are bids for support assessed, with the lowest bid winning. The design aims to limit public spending while giving developers protection against low prices. Together, the two farms are expected to generate up to 7,441 GWh of electricity a year.
Read More: https://oceaneconomist.com/articles/shearwater-totalenergies-angola-4d-seismic
Grid Connection and Timeline
Transmission system operator TenneT is building the grid connection that will link the two sites to the onshore network. Gamma-A and Gamma-B will share a single offshore platform with a 2 GW direct current connection to shore. Sharing one platform makes better use of the grid and reduces the work and time needed for installation. The wind farm developers will connect their projects to that platform.
The wind farms are expected to start operating around 2032. Grid availability is often a constraint on offshore wind timelines, so a connection planned reduces risk for bidders. Developers will still need to secure turbines, foundations, installation vessels and port capacity. Those supply chain commitments depend on the tender delivering firm awards.
Industry Calls for Predictability
Industry association NedZero said the tender comes at a critical moment for the sector. Chairman Jan Vos said the coming weeks will show not only whether companies bid, but at what prices and with what risks attached. Bids close to the cap would suggest costs remain high, while bids well below it would point to stronger competition. A weak response would raise questions about the Dutch rollout targets.
Vos said companies are making long-term investments in staff, manufacturing capacity, vessels and port facilities. To justify those investments, he said, the industry needs continuity, steady volumes and a predictable rollout of new sites. The Netherlands has been one of Europe's leading offshore wind markets. The results of the Gamma tenders will be closely watched across the North Sea region.