Carnegie Clean Energy has deployed the buoyant actuator of its CETO wave energy converter at the Biscay Marine Energy Platform (BiMEP) off Armintza in Spain’s Basque Country. The deployment is the first offshore stage of the ACHIEVE Program and is designed to validate marine logistics, authorizations, and the device’s behavior in real ocean conditions. It also unlocks funding milestones ahead of a full grid-connected deployment planned for spring 2027 in Europe.

 

Stage 1 Deployment

 

A local Basque fabricator built the buoyant actuator in three modular sections and transported it by road to the Port of Bilbao. There, the sections were assembled on the quayside before cranes lowered the unit into the water and docked it alongside the quay. On Saturday 14 November, it was towed to Carnegie’s pre-permitted berth at BiMEP and connected to a purpose-built mooring and anchor system. The unit will remain on site for a short period before being retrieved at the end of the current weather window.

Stage 1 is deliberately short, as its main goals are to validate offshore logistics, installation and retrieval rather than generate power. Retrieval and tow back to port will be scheduled around suitable weather and vessel availability. Bringing the unit safely back to port will itself test logistics and supply chain capabilities. Over the European winter, the buoyant actuator will be kept onshore in port.

 

Building Local Capability

 

As part of the deployment, Carnegie secured the necessary clearances from port and maritime authorities. These covered quayside assembly, heavy lifting, port and offshore transit, and offshore installation. Working through these processes established practical local supply chain workflows and logistics. That experience will reduce risk and uncertainty for the full system deployment next year.

The team carried out the anchor and mooring installation, towing, vessel coordination and offshore hook-up at Bilbao and BiMEP. The operation was led by Carnegie’s Chief Technology Officer, who previously deployed the company’s CETO array in Australia and has led CETO design since then. Carnegie says the campaign has given its whole team valuable local offshore experience in the Basque Country. This expands the company’s ability to manage complex offshore campaigns in the future.

 

The Path to Grid Connection

 

While the buoyant actuator is in port over winter, the power take-off modules will undergo final onshore testing in Bilbao. These tests will run the power take-off and electrical modules under simulated ocean conditions to check mechanical, electrical, control and communications functions. The power take-off has been assembled with specialist supplier SKF. Thorough onshore testing reduces the risk of problems once the system is at sea.

Stage 2, planned for European spring 2027, will see the fully integrated CETO system deployed at BiMEP and connected to the grid. Although CETO is designed to operate year-round, prototypes are typically first deployed in the calmer late spring and summer months. This allows engineers to resolve any early problems more easily before exposing the device to harsher conditions. Once fully deployed, the unit is expected to operate at BiMEP for two years, gathering data to support commercialization.

 

Read More: https://oceaneconomist.com/articles/subsea-expo-2027-aberdeen

 

How CETO Works

 

CETO is a fully submerged point absorber wave energy device. A buoy sits a few meters below the surface and moves with the orbital motion of passing waves. This motion drives a power take-off system that converts the movement into electricity. Operating below the surface protects the device from the most extreme wave forces at the surface and reduces its visual impact.

The buoyant actuator is the system's prime mover, capturing energy from the waves. BiMEP is an established test site for wave and offshore energy technologies, with grid connection and permitting already in place. Testing at such a site lets developers focus on technology performance rather than securing new consents. For Carnegie, a successful two-year campaign would provide key evidence for investors and future customers.

 

Managing Technology Risk

 

Wave energy has struggled to reach commercial scale, with many developers facing technical setbacks and high costs. A staged approach with extensive onshore testing is designed to reduce risk on a project involving significant technology advances. Successful completion of Stage 1 also unlocks key funding milestones under the ACHIEVE Program. This financial support is important for a small listed developer like Carnegie.

Carnegie Chief Executive Jonathan Fiévez said seeing the buoyant actuator offshore at BiMEP was a proud moment for the company. He said it took a major effort from the Bilbao team to make Stage 1 a success. Fiévez said the experience has strengthened the team’s capabilities and put the company in a more certain position ahead of Stage 2. He added that the project involves major technological leaps, so staging it and conducting substantial onshore testing are important for managing risk.

 

Source: Carnegie