ELWIND Completes Initial Public Consultations on Latvian Offshore Wind Park

ELWIND Completes Initial Public Consultations on Latvian Offshore Wind Park
Guest Contributor

Guest Contributor

Contributor

8 min read

The ELWIND joint Latvian-Estonian offshore wind project held its first public consultation meetings in Ventspils, Pāvilosta, and Ziras between 4 and 6 November 2026, attracting around 170 residents, municipal officials, and other stakeholders. Discussions focused on potential impacts on the Baltic Sea environment, the coastal landscape and residents, as well as economic benefits and onshore cable routes. More than 20 environmental and technical studies are underway to provide the data needed for future project decisions.

 

The Consultation Meetings

 

The meetings took place at Pārventa library in Ventspils, the Pāvilosta culture center, and the Saulgrieži community center in Ziras. Project representatives and researchers briefed participants on the progress of studies, early findings and the next stages of development. Coastal residents particularly wanted research-based answers on impacts on fish, birds, marine mammals and the coastal landscape. Questions were also raised about turbine decommissioning, infrastructure and benefits for local communities.

Several questions can only be answered fully once studies are complete. Jānis Ločmelis, Head of the ELWIND Project Division at the Investment and Development Agency of Latvia (LIAA), said offshore wind offers new opportunities for Latvia but must be developed based on thorough research and open dialogue. He said the agency cannot promise specific benefits until technical solutions and impacts have been assessed. Its current task is to gather reliable data and ensure residents’ questions are taken into account.

 

Environmental and Technical Studies

 

The studies cover seabed geology, weather conditions, biodiversity, water quality, grid connection, and other factors needed to assess the wind park’s impacts. Early findings are available from some studies, while data collection continues in others and several have yet to be procured. Some studies require observations across multiple seasons to capture how the marine ecosystem changes through the year. Baseline surveys of migrating birds, for example, have been carried out from a research vessel based in Pāvilosta.

The results will add to scientific knowledge of the Baltic Sea in areas where detailed studies have been limited. Oskars Beikulis, Lead Consultant at environmental consultancy Estonian, Latvian & Lithuanian Environment, explained that the environmental impact assessment is strictly regulated by law. It establishes baseline conditions, forecasts potential changes, assesses alternatives,s and identifies measures to reduce harmful impacts. The assessment also sets out monitoring needed during construction and operation.

 

Site Location and Landscape

 

The study area for the Latvian part of ELWIND lies in the Baltic Sea between Liepāja and Ventspils, about 22 to 3 kilometers from the coast. In 2025, the area was moved more than seven kilometers further offshore, based on findings from the LIFE REEF project run by Latvia’s Nature Conservation Agency. The move reduces risks to valuable marine habitats and avoids overlap with a potential future marine protected area. An earlier consultation in 2023 covered the site’s original location closer to shore.

The greater distance from the coast will also reduce the wind park’s visual impact, although this will be assessed in detail during the environmental impact assessment. The final turbine layout, number of turbines, and technical design have not yet been decided. These will be determined by the developer selected through a future auction. Visual impact is often a key concern for coastal communities near offshore wind projects.

 

Read More: https://oceaneconomist.com/articles/slb-var-energi-drilling-contrac.t

 

Onshore Cable Routes

 

At the final meeting in Ziras, a major topic was the planned onshore cable routes to the Ziras substation. Residents raised concerns about cables running close to private properties and possible conflicts with planned upgrades to the village’s water and sewerage networks. They also questioned the combined impact of several energy projects in the area. Cumulative impacts are an increasing concern as more energy infrastructure is planned along the Kurzeme coast.

Project representatives said preliminary studies are still underway, ay and possible route options are being assessed. The cable routes are intended to be agreed voluntarily with landowners. If agreement cannot be reached, alternative technical solutions or routes will be considered. Early engagement on cable routes can help avoid delays and disputes later in the project.

 

Economic Benefits for Coastal Areas

 

Under current rules, wind power producers must pay EUR 2,500 per megawatt of installed capacity each year for local community development. The Latvian part of ELWIND could have a capacity of 500 to 1,000 megawatts, implying total annual payments of about EUR 1.25 million to EUR 2.5 million once operating. The payments would go to relevant municipalities and to households meeting certain criteria. The final amount will depend on installed capacity, turbine locations and the rules in force at the time, so the figures are estimates rather than guaranteed income.

Further benefits could come from local companies providing construction and maintenance services, new jobs and demand for port and logistics services. Ports in Kurzeme, including Liepāja, Ventspils and Pāvilosta, could benefit, although no specific choices have been made. Ločmelis said the aim is to ensure offshore wind creates opportunities for Latvia’s coastal areas. He said the agency cannot yet promise a specific number of jobs or investment in a particular port, as these will depend on study results and future decisions.

 

Next Steps

 

Questions, proposals and objections from the consultations will be compiled and sent to Latvia’s State Environmental Service for evaluation. Well-founded proposals will be considered in further assessment of the project and preparation of the environmental impact assessment documents. Written proposals could be submitted until 13 November 2026. The project team said continued engagement with residents will remain important as studies are completed.

ELWIND is a cross-border project between Latvia and Estonia with a combined planned capacity of up to 2 gigawatts. LIAA and the Estonian Environmental Investment Center lead it, working with Latvia’s Ministry of Economics and Estonia’s Ministry of Climate. An auction to transfer development rights to a qualified developer is planned for 2029, with operations targeted for 2035. The project aims to strengthen regional energy security and support the shift to renewable energy in the Baltic states.

 

Source: ELWIND Offshore