Money set aside to decommission UK offshore wind farms varies by up to ten times between projects using turbines of similar size. That is the finding of new research by energy consultancy Xodus and its offshore renewables engineering arm, Evolv Energies. The study reviewed the accounts of 37 operating wind farms with almost 2,500 turbines. It concludes that published cost estimates cannot be reliably compared, just as the earliest UK sites approach the end of their design life.

 

Wide Variation in Provisions

 

Xodus launched the whitepaper, Benchmarking Offshore Wind Decommissioning Provisions, on 24 November at Offshore Energies UK's Offshore Decommissioning Conference. It analyses decommissioning provisions disclosed in Companies House accounts between 2019 and 2025. To allow comparison, Xodus converted each project's provision to a cost per turbine. The results showed wide spreads within each turbine size band.

For projects with turbines below 4 MW, provisions ranged from £180,000 to £1.83 million per turbine, a spread of about ten times. For turbines above 8 MW, the range was £750,000 to £4.56 million, about six times. Average provisions rose from roughly £900,000 per turbine for the smallest machines to around £1.5 million for the largest. Xodus said gaps of this size point to differences in the assumptions and methods used, so the figures should not be compared directly without understanding what lies behind them.

 

Estimates Shifting Over Time

 

The study also found large changes in individual estimates during the review period. One project's reported liability rose more than sixfold. Others increased only slightly, and several were cut. Part of the downward revisions reflects higher discount rates, which reduce the present value of costs expected many years in the future.

Olivier Mette, Head of Advisory at Xodus, said some variation was expected because every wind farm is different. What stood out, he said, was the scale of the differences between projects with similar turbines, suggesting their underlying assumptions differ widely. He added that some estimates appear to rest on more detailed engineering work than others. Unstable estimates make it harder for owners and investors to judge long-term liabilities.

 

Uncertainty Over Seabed Rules

 

Mette said the regulatory framework remains unsettled, particularly on the condition in which the seabed must be left after removal. The required end state could include removing foundations, cables and scour protection, or leaving some structures in place. Each option carries very different costs. Until regulators set clearer requirements, owners must base provisions on their own assumptions.

Elvin Eren, Renewables Advisory Lead at Xodus, said reported provisions are a useful starting point but are discounted estimates based on differing assumptions. These cover the scope of removal, its timing and the required seabed condition. He said owners, investors and lenders should treat the figures as the start of due diligence, not the final answer. Eren recommended testing them against clearly defined removal scenarios.

 

Read More: https://oceaneconomist.com/articles/baker-hughes-mcdermott-ichthys-subsea

 

Turbines Nearing End of Life

 

The findings come as the UK's first generation of offshore wind farms ages. Assuming a 25-year design life, 532 turbines in the benchmark will reach the end of that life by 2036. By 2041 the figure rises to 1,285, just over half of the turbines reviewed. Some early projects were designed for only 20 years, which could bring these dates forward.

Owners will need to decide whether each site is life-extended, repowered with new turbines, or fully decommissioned. Each choice depends on a credible estimate of removal costs. Unlike depleted oil and gas fields, where removal is usually the only option, wind sites can keep their value after the original turbines retire. Their seabed leases, grid connections and infrastructure can continue to support clean power generation and energy security.

 

Call for Transparent Disclosure

 

The study calls for a more transparent and consistent approach to estimating and disclosing decommissioning costs, including the assumptions used. It argues that reliable cost estimates and clear regulation depend on each other. Policymakers need credible cost data to set rules, while owners need regulatory certainty to define scopes and produce robust estimates. Mette said an accurate benchmark gives operators, investors, government and seabed owners a common reference point before the earliest sites reach their decision points.

Xodus has completed more than 500 decommissioning scopes in over 20 countries. Between 2021 and 2025, it supported more than two-thirds of UK oil and gas decommissioning regulatory submissions. The company is applying that experience to offshore wind, including independent reviews of wind farm decommissioning programs for the Scottish Government. It also co-authored Offshore Energies UK's Designing for Decommissioning of Offshore Wind Guidelines.

 